5225 Vessey Road - Phase 5

 

Phase 5 of the building process is where the exciting part of the construction begins.  During this phase, the Raton Road home will have the framing completed as well as the exterior and interior.

 

• Framing
• Fireplace install
• Roof Dry In
• Gutter and Downspouts
• Window Install
• Plumbing Rough
• Mechanical Rough
• Plumbing and Mechanical Inspection
• Electrical Walk Through
• Electrical Rough
• Electrical Inspection
• Electrical Service
• Garage Doors Installed
• Stucco/Masonry Lathe
• Phone/AV/Cable Wiring
• Radiant Tube Install (if applicable)
• Pour Lightweight concrete (if applicable)
• Frame Inspection
• Insulation
• Insulation Inspection
• Drywall
• Shelving
• Stucco Brown Coat
• Paint Exterior
• Masonry Exterior

 

Copyright © 2010. Colorado Springs Home Builder. Designed by springshomes.com